When Travelodge were planning the development of a new venue in Cheshire Energy Gain UK were commissioned to provide a full energy compliance report, design, supply, install & commission a Solar Photovoltaic System. Travelodge needed to ensure that they met Sbem renewable calculations, as well as ensure that running costs were kept to a minimum by implementing the latest energy reduction technologies.
Project Detail
Client Travelodge
Sector Hospitality
Scope Provide Full Energy Compliance Report, Design, Supply, Install & Commission Solar Photovoltaic System
Technology Solar Photovoltaics
Location Chester
Site Details
Capacity 17.60KWp Feed Three Phase
Azimuth 30 Degrees Pitch 35 Degrees
Shading None Access Scaffold
Components
Mounting On-Roof Mounting System Hilti
Solar Modules Sharp ND 220 Qty of Solar Modules 80
Inverter SMA 17000TL Qty of Inverters 1
Generation Data
Estimated Annual Output 855 KWP/KWh p/a Carbon Saving 7,894 KgCo2e p/a
*Figures based on PVGIS Data *Figures based on 0.5246 KG CO2 per